Airport

  • Airfield study, Broujerd Airport


    Preliminary studies and site selection, airfield civil works first phase study, phase II civil works study. In first operation phase the project aircraft is F100 and runway length 2750 M & width 45 M with two 7.5 M shoulders, the apron in first phase is 120 * 112.5 M. in the next operation phase the project aircraft is A300- 600, runway length 3500 m &width 45 M with two 7.5 M shoulders.

    • Client:
      Iran Airport Company
    • Contract value:
      Rial
    • Contract Duration:
      4 Mo
    • Project Manager:
      Mrs.Banafsheh Nourbakhsh
  • Shoulder side strip and surface water collection, Noshahr Airport

    Runway preparation with75 M width on both side of runway aux and construction of open water channel on each side of runway.

    • Client:
      Mazandaran airports office
    • Contractor:
      Eskelsazan kadoos Co.
    • Start time:
      1393/3/10
    • Finish time:
      1393/6/10
    • Project Manager:
      Mrs.Banafsheh Nourbakhsh
    • Construction Project Manager:
      Mr.Saeed Kariminejad
  • Apron extension study & runway extension & surface water collection, Sari Airport

    Apron development with additional 30,000 Sq M, 40 Cm concrete pavement, runway extension 250 M with asphalt toping. Construction of shoulder side strip and open water conveyance channel on each side of runway.

    • Client:
      Mazandaran airports office
    • Contract value:
      0Rial
    • Project progress:
      100 %
    • Project Manager:
      Mrs.Banafsheh Nourbakhsh
    • Construction Project Manager:
  • East Apron extension, study &supervision, BandarAbas Airport

    Passenger apron in 40,000 Sq M area with 38 Cm concrete top layer.

    • Client:
      Iran Airport Company
    • Contractor:
      Tonelsazano of Iran Co.
    • Contract value:
      59.000.000.000Rial
    • Contract Duration:
      8 mo
    • Physical progress:
      95 %
    • Project Manager:
      Mrs.Banafsheh Nourbakhsh
    • Construction Project Manager:
      Mr.Saeed Kariminejad
  • Airfield construction study and supervision, Gonabad Airport

    Airfield construction including runway, taxiway, apron ,shoulder strip and surface water collection.

    • Client:
      Iran Airport Company
    • Contractor:
      kayhan rah sharq Co.
    • Contract value:
      60.000.000.000Rial
    • Contract Duration:
      12 Mo
    • Physical progress:
      95 %
    • Project Manager:
      Mrs.Banafsheh Nourbakhsh
    • Construction Project Manager:
      Mr.Saeed Kariminejad
  • Airfield rehabilitation and re-pavement supervision, Rafsanjan Airport

    Runway, taxiways and apron rehabilitation, including cold asphalt retrieving with 25 Cm thickness and asphalt pavement in 13 Cm.

    • Client:
      Iran Airport Company
    • Contractor:
      Pe Bell Co.
    • Contract value:
      58.000.000.000Rial
    • Contract Duration:
      9 mo
    • Start time:
      1387/9/5
    • Physical progress:
      100 %
    • Project Manager:
      Mrs.Banafsheh Nourbakhsh
    • Construction Project Manager:
      Mr.Saeed Kariminejad
  • Study review and finalizing, Makoo Airport civil works

    Discription

    • Client:
      Makoo free zone authority
    • Contract value:
      0Rial
    • Contract Duration:
      Mo
    • Project Manager:
      Mr.Hosein Javaheri
    • Construction Project Manager:
      Mr.Hosein Javaheri
  • Saqez Airport airfield project

    Airfield rehabilitation.

    • Client:
      Iran Airport Company
    • Contract value:
      0Rial
    • Contract Duration:
      Mo
    • Project Manager:
      Mr.Hosein Javaheri
    • Construction Project Manager:
      Mr.Hosein Javaheri
  • 9 مشخصات پروژه

    Discription

    • Client:
      Iran Airport Company
    • Contract value:
      20.000.000.000Rial
    • Contract Duration:
      12 ماه
    • Project Manager:
      مهندس معصومه عطایی
    • Construction Project Manager:
      مهندس کورس عراقی
  • 10 مشخصات پروژه

    Discription

    • Client:
      Iran Airport Company
    • Contract value:
      20.000.000.000Rial
    • Contract Duration:
      12 ماه
    • Project Manager:
      مهندس معصومه عطایی
    • Construction Project Manager:
      مهندس کورس عراقی